Each unit carries a list of equipment: hose loads, ladders, appliances such as a master stream or a deck gun, and agents such as foam concentrate or dry chemical. A hose load can also have a slot, the place on the truck it rides: a crosslay, a lane of the rear bed, or a lane of the front bumper. Program a unit's loads once, and a line laid from one can start right at its slot, in the load's color, while the app keeps track of the hose left in each bed.
Open a unit's equipment
In Admin, open the Vehicles & Equipment tab, find the unit, and press Equipment on its row. The Equipment Editor opens with a to-scale, top-down drawing of the unit beside the list of everything it carries.
Only a department admin and above sees the Vehicles & Equipment tab, so only they can change a unit's loads.
A new engine, truck, or quint starts with standard equipment. None of it sits in a slot until you set one.
Set up a load
Add an item with the form under the list, or open an existing one to change it. Each item has a Type (a handline, LDH, hard suction, ladder, aerial, master stream, blitz fire, trash line, hotel pack, deck gun, foam concentrate, dry chemical, or other item), a Label your crews know it by, a Length in feet, and a Deploy From side. The sides on offer depend on the type: front, driver's, officer's, rear, top, or aerial.
- Hose loads, meaning handlines, LDH, hard suction, master streams, blitz fires, trash lines, and hotel packs, also have a Diameter. Water Supply counts a line of 3 inches or more, and a load with no diameter set counts only when it's LDH. Hard suction counts at any size. A new Hard suction item starts at 20 feet, 6 inches, and black: it is what an engine or quint drafts with. The map draws every hard suction line with a white outline and a gray spiral, whatever its color, so it shows on satellite imagery. See Draft with hard suction.
- Every type except an aerial has a Color row of swatches. A hose load's lines are drawn in its color.
- A ladder also has a Ladder type: straight (single), roof, extension, folding (attic), combination, pole (Bangor), Fresno, or other. Its color row starts with gray, the color a ladder draws in until you pick another. A ladder placed on the map, in Street View, in either 3D view, and the dot beside it in the equipment lists show its color. A ladder that doesn't have a type yet, such as one saved before ladder types were added or one a new unit starts with, draws gray, and opening it shows a type read from its label, such as extension for "35' extension". Neither is saved until you press Update and save the equipment. A new ladder named for its type, such as "24' extension", is renamed when you change its type; a name you typed is kept.
- A Foam concentrate or Dry chemical item carries an amount instead of a length: its Quantity is gallons of concentrate on a foam item and pounds of agent on a dry-chemical item, and it never lays as a line.
- Every item has a Preconnect checkbox. On a handline, LDH, trash line, or hotel pack, checking it makes the load single-use: laying it once puts it in use. Left unchecked, the load is a bed that a crew can lay from more than once, until its length runs out. See Lay from one hose bed more than once.
Put a load in a slot
A hose load that comes off the front, the rear, or either side also has a Slot field that names where it rides:
- Crosslays 1 to 4, over the pump panel and numbered front to rear, for a load pulled to the driver's or officer's side.
- Five lanes across the rear bed, for a load off the rear.
- Three lanes across the front bumper, for a load off the front.
Left and right are the truck's own: left is the driver's side, at the rear as at the front. A load with no slot starts at the middle of its side (the pump panel, on an engine), or at the center of the front or the rear.
To pick a slot, choose it from the Slot list, or press an open slot on the drawing, which outlines each free slot on the load's side. Choosing a slot that another load already holds shows a warning under the form that names that load. A crosslay counts as one bed whichever side its line is pulled to.
Add a dead load
A dead load is extra hose bedded with a preconnect to extend its line, without being connected to a discharge. A blitz fire, for example, might carry a 200-foot preconnect and 100 feet of dead load, used to extend the line or laid on its own as supplementary hose.
Program the dead load as an item of its own:
- Add a handline, LDH, trash line, or hotel pack with Preconnect unchecked, and set its Length to the dead load's length, for example 100.
- Under Dead load for, choose the line it extends. The list offers the unit's preconnects, blitz fires, and master streams. On a new item, the choice also puts the dead load in that line's slot and color, takes the line's diameter when it has one, and names the item after the line unless you already typed a label.
- Press Add, then Save Equipment.
The list names the line under the item, for example "Dead load for Blitz fire". A dead load that shares its line's slot doesn't set off the slot warning. To unlink one, choose Not a dead load; checking Preconnect unlinks it too, because a preconnect is never a dead load.
- A dead load extends its line only at the same Diameter. When both have a diameter and they differ, the form says so. A diameter that isn't set rules nothing out.
- Removing the item a dead load extends, with Remove, leaves the dead load on the unit as an ordinary bed. Copy from another unit keeps each dead load with its own line.
Change, reorder, or remove a load
To change a hose load, press its mark on the drawing: a solid mark sits in a slot, and a dashed one has none. To change any item, press Edit beside it in the list. The item opens in the form, where Update takes the place of Add, and Cancel Edit leaves the item as it was and clears the form.
The up and down arrows beside an item in the list move it. That order is the order a crew sees when deploying from the unit. Remove takes the item off the unit's layout.
Copy a layout from another unit
For a unit loaded like another, press Copy from another unit, choose the unit to copy under Copy from, and press Copy. The list offers the department's other units that carry equipment. A copy replaces the whole list, ladders included, rather than adding to it, so the app confirms first; on a unit that already has equipment, it asks "Replace this layout?". Nothing is saved until you save the layout.
Save the layout
Changes stay in the editor until you press Save Equipment. Until then, the editor reads "Unsaved changes". Cancel closes the editor without saving. If a save fails, your changes stay in the editor and it reads "Not saved. Your changes are still here, so try again."
Lay a line from its slot on the map
On a placed unit whose position is saved, in edit mode with the Select tool, zoom in to the map's two closest zoom levels. Each hose load that has a slot shows as a chip in its color beside the truck, with a thin leader to the point its line starts from. Chips need the member role or above, and they hide while a line or ladder is being deployed.
- With a mouse, press a chip and drag. The line's first stroke starts at the slot, in the load's color.
- With touch or the keyboard, tap the chip, or press Enter or Space on it. The draw opens at the slot, and you draw the line from there.
A chip dims and can't be pressed once its load is in use: a bed with less than a whole foot left, or a single-use load, such as a preconnect, that's already laid.
When the draw opens with no stroke under way, as it does after a tap on a chip or Deploy in the equipment list, your first press decides where the line starts. A press near the slot starts it exactly at the slot. A press anywhere else on the truck starts it where you pressed, which is how a line shows it went around the truck. A press off the truck keeps the start at the slot.
Wherever it starts, the line keeps its load's color on the 2D map, in replay, and in 3D, and the PDF from Export as PDF lists it beside a swatch of that color. The Equipment tab and the deploy list show a load's slot under its name, for example "Crosslay 1 · Driver's" or "Rear left".
Lay a line from the equipment list
Select a placed unit whose position is saved and press Deploy Equipment to list its hose loads and ladders. Deploy beside an item starts laying it, from its slot when it has one. An item marked in use has no Deploy button: a bed with less than a whole foot left, or a single-use item already deployed, such as a preconnect, master stream, blitz fire, ladder, or aerial.
When a lay needs more hose than is left
A lay longer than the hose left never stops the line. While you draw, as soon as the line needs more hose than is left in its bed, a warning gives both numbers, and you keep drawing:
This lay needs … ft; … ft is left in the bed.
A preconnect or another single-use load warns the same way, with the load's own length: "This lay needs … ft; the preconnect is … ft." or "This lay needs … ft; the load is … ft." The warning appears under the drawing bar at the top of the map, and the bar's length gauge turns red; both follow the line under your pointer or finger. Dragging a point of a line already laid past what's left shows the same warning as a toast.
A line you continue up or down a stair to another floor is one line in two runs, and the app measures it that way. Each run can use what the other run leaves on the load, less 15 feet for the stairs, and a warning names both numbers: "This lay needs … ft; … ft is left of the preconnect's … ft." A 200-foot preconnect laid 120 feet to the stairs leaves 65 feet for the floor above. A bed counts the 15 feet of stairs in the hose it has left, too. Each run's row in the Equipment tab and in the PDF reads the whole line, both runs and the stairs over the one preconnect, for example "215'/200' across 2 floors".
Extend, on a line's right-click menu or on the menu at its last point, goes straight back into drawing from where the line ends, and warns the same way when the line needs more hose than is left.
Extend a line with hose from the unit
When a line laid from a preconnect runs long, the warning offers hose from the rest of the unit to extend it. It appears under the drawing bar, and on the toast after you drag a point of a laid line past its hose. Under the drawing bar it appears as soon as the line runs long, while you're still drawing, and you press it once you lift. While you draw, the drawing bar and everything under it fade so you can see the map and draw across them, and the warning fades less so you can still read it. The map controls along the right side of the map, from the map type switch down to zoom, fade the same way, so a line can pass under them. They all come back when you lift. A press adds the hose without opening a dialog, and you keep drawing.
The offer lists the unit's loads that still have hose left and fit the line:
- The line's own dead load.
- Any bed at the line's Diameter: a handline, LDH, trash line, or hotel pack with Preconnect unchecked. That includes a dead load bedded for another line. When the bed or the line has no diameter set, LDH fits only LDH, and any other hose fits any other hose.
A preconnect is never on the list: its hose is its own line's.
With one load to offer, the warning shows a single button: Add N' dead load for the line's own dead load, or Add N' from LOAD for any other load, where N is the feet it adds and LOAD is the load's label, or where it rides on the truck when it has no label. Two loads with the same label also say where each rides. With two or more, a list labeled Add hose from names each load with what it has left, LOAD · N' left, and the button beside it adds hose from the load you pick. Once the list or its button has focus, both work from the keyboard: the arrow keys change the pick, and Enter adds the hose. While the map itself has focus, Tab can step between the placed units instead, so reach the list with Tab from another control, such as a toolbar button.
The toast after a drag waits while you use it: it stays up while your pointer is over it, while its list or button has focus, and while its list is open. After a press, it shows the line's new numbers in the same place, and if it added no hose, it says why. For example, while you're extending or redrawing that line, it asks you to add hose from the drawing bar. A second press right after the first does nothing, so a double-click adds hose once.
The list puts first a load the line already took from, on this run or on another run up or down a stair, then the line's own dead load, then the unit's other loads. Within each, a load with enough hose to cover the stretch comes before one without, and among those without, the one with the most left comes first.
Hose comes off in 50-foot sections. One press adds as many sections as the line is short, or all that's left on that load if that's less, so the rest stays on the truck. A 270-foot stretch on a 200-foot preconnect with 100 feet of dead load adds all 100 feet and clears the warning; a 230-foot stretch adds 50 feet and leaves 50 on the truck. If the line still needs more, the warning stays, names every part, and offers what the unit has left:
This lay needs … ft; the preconnect is … ft + … ft dead load.
The warning names hose from any other load too, for example "+ 50 ft from Static bed".
When you press Done, the line keeps only the 50-foot sections it still needs past its preconnect, never more than it took from a load, and the rest goes back on the truck: a line redrawn to 230 feet keeps 50 feet, and one redrawn inside its preconnect gives all of it back. Hose added first is kept first. Done also keeps no more than each load has left, so hose that another line holds is never counted twice.
While the line fits, the line under the drawing bar says what it carries, for example "200' preconnect + 100' dead load + 50' from Static bed". The line's row in the Equipment tab and its row in the PDF read the same way, and the line keeps its hose in replay. Adding hose to a laid line doesn't change when the line went out, so its Time to target stands. A blitz fire or master stream without Preconnect checked is called a load instead, in the warning and everywhere else: "200' load + 100' dead load".
- Hose a line took from a load is no longer on the unit. The deploy list shows what's left, for example "50' left of 100'", and the load's chip dims once none is left. A line laid from that load on its own leaves that much less to extend with.
- A line can take hose from more than one load, and so can a line continued up a stair.
- Undo takes it back. Hose added while you draw becomes part of the lay when you press Done, and one undo then takes back the lay and all the hose it took together. Undo pressed before Done takes back your previous action instead, and the added hose stays on the lay. Added to a laid line from the toast, one undo removes just that hose.
- The member role and above can add hose, the same as laying the line.